Current Work

Pavement restoration on Main Street East and Elm Street is complete. Overnight paving along Main Street East, through the Elm Street intersection and into the Balsam Lane parking lot, wrapped up Wednesday, September 30, followed by daytime paving on the majority of Elm Street on Thursday, October 1. Elm Street is now fully open.

A small section of the mainline trench near Oak Street remains to be restored and will be completed when Mountain Street is paved following watermain installation.

Watermain installation by directional drilling was completed on Rossmore Avenue this week, while work on Main Street West, west of Forty Mile Creek, began Wednesday.

The soil stockpile at the pool parking lot has been removed. The area will be used temporarily for additional stockpiling during upcoming night work at the Mountain Street intersections, with material removed shortly after it is placed.

Looking Ahead – Week of October 5

Watermain Installation: Main Street West (Forty Mile Creek to just beyond Patton Street)

Watermain installation will continue throughout the week and is expected to be completed by the end of the week. The servicing crew will join the work early to mid-week.

Night Work: Elm Street and Mountain Street Intersection

Crews will complete work at the intersection overnight, tentatively from Wednesday, October 7 until Saturday, October 10, from 8:00 p.m. to 6:00 a.m. The intersection will reopen each morning at approximately 6:00 a.m. Soil from the night work will be temporarily stockpiled at the pool parking lot, as receiving sites are not open overnight.

Once the intersection work is complete, Mountain Street between Elm Street and Main Street will be fully closed for approximately four weeks so crews can complete the work during the daytime.

Traffic Impacts

  • Main Street West (Forty Mile Creek to just beyond Patton Street): One lane of alternating two-way traffic during daytime work hours.
  • Main Street West and Christie Street: The left-turn lane remains closed.
  • Elm Street and Mountain Street intersection: Closed to through traffic from 8:00 p.m. to 6:00 a.m. during night work. Detours will be in place for cars and heavy trucks.
  • Elm Street and Mountain Street: Accessible to local traffic only, as dead-end roadways, while the intersection is closed.
  • Mountain Street (Elm Street to Main Street): Full closure for approximately four weeks following the night work, with detours in place around the clock.
  • Downtown parking lots remain accessible.
  • Elm Street: Fully open.

View the Main Street West traffic plan | View the Elm Street and Mountain Street construction plan | View the car detour plan | View the truck detour plan

Downtown remains open for business throughout construction.

The Construction Passport has now wrapped up. Thank you to everyone who participated and supported our downtown businesses!

There's still plenty happening downtown this fall. The final Grimsby Farmers' Market of the season takes place Thursday, October 8, at the Major Refrigeration Peach King Centre behind Town Hall, and the Moonlight Market & Movie comes to Coronation Park on Saturday, October 17, from 6:00 p.m. to 9:00 p.m.

Learn more: www.letstalkgrimsby.ca/dr-construction

Questions? Email DTreimagined@grimsby.ca.

Follow along on Facebook and Instagram @downtownreimagined.

Subscribe Back to News Search

Contact Us

Town of Grimsby
160 Livingston Avenue
Grimsby ON, L3M 0J5
Phone: 905-945-9634
Fax: 905-945-5010

Sign up to stay up to date with news from the Town of Grimsby

Stay up to date on the Town's activities, events, programs and operations by subscribing to our News Alerts.